Question: Which process involves comparing actual project results against the agreed-upon project management plan? a) Monitor and Control Project Work b) Perform Integrated Change Control c)
Which process involves comparing actual project results against the agreed-upon project management plan?
a) Monitor and Control Project Work
b) Perform Integrated Change Control
c) Direct and Manage Project Work
d) Control Scope