Question: While estimating the activity durations on your project, you come across a similar project completed by your organization last year. To save time, you use
While estimating the activity durations on your project, you come across a similar project completed by your organization last year. To save time, you use information from this project to help estimate activity durations. This is an example of which tool or technique?
A: Bottom-up estimating B: Analogous estimating C: Parametric estimating D: Three-point estimating