Question: While managing a large project in your organization, you realize that your project team requires training in contract administration because you will be awarding several
While managing a large project in your organization, you realize that your project team requires training in contract administration because you will be awarding several major subcontracts. After you analyze your project requirements and assess the expertise of your team members, you decide that your team will need a one-week class in contract administration. This training should—
a. Commence as scheduled and stated in the staffing management plan
b. Commence as scheduled and stated as part of the procurement management plan
c. Be scheduled if necessary after performance assessments are prepared and after each team member has had an opportunity to serve in the contract administrator role
d. Commence as scheduled and stated in the team development plan