Question: Assume that on your project, you are using earned value management. You also are conducting performance reviews. You recognize, though, that an important aspect of
Assume that on your project, you are using earned value management. You also are conducting performance reviews. You recognize, though, that an important aspect of cost control is determining the cause and variance compared to the cost baseline. You have found that—
a. The most frequently analyzed measurements are CPI and SPI
b. The milestone method is the most accurate way to assess performance using earned value
c. Graphical techniques will enhance how the information is received
d. The range of acceptable variances will tend to decrease over time