Question: While planning, the project manager realizes the project has many unknowns. What should the project manager plan for? a) Reserves for identified risks b) More

While planning, the project manager realizes the project has many unknowns. What should the project manager plan for?

a) Reserves for identified risks

b) More detailed risk analysis

c) Reserves for unidentified risks

d) More team meetings to discuss potential risks