Question: Which of the following scheduling techniques considers both resource optimization and uncertainty in estimating activity durations? a) Critical Path Method b) Critical Chain Method c)
Which of the following scheduling techniques considers both resource optimization and uncertainty in estimating activity durations?
a) Critical Path Method
b) Critical Chain Method
c) Program Evaluation and Review Technique
d) Gantt Chart