Question: You are a project manager on a large software project using the earned value reporting system to manage your project. At this point in time,

You are a project manager on a large software project using the earned value reporting system to manage your project. At this point in time, the EV is

$24,000, the BAC is $97,000, the PV is $29,000, and the AC is $45,000. What is the percent complete?

A: 30%

B: 25%

C: 46%

D: 53%