Question: USING THE RISK REGISTER CASE STUDY 3 . 1 An organization with an Earned Value Management System ( EVMS ) contractual requirement for a large
USING THE RISK REGISTER
CASE STUDY
An organization with an Earned Value Management System EVMS contractual requirement for a large project must demonstrate to its customer that the EVMS is being used to manage the performance on the project. A subproject has been established to conduct the earned value training for the project personnel.
The objective of the subproject has been established as:
To enable each manager to successfully demonstrate their knowledge and use of Earned Value Management policies, procedures, processes, software tools and their respective responsibilities in a formal review of the project's EVMS by the customer." A primary project time line includes the following activities:
Day
Contract goahead"
Day
Develop EV Concepts Policy
Day
Develop EV Concepts Training Plan
Day
Identify and assign fifty managers
Day
Review and approve EV Concepts Training Plan
Day
Managers implement EVM System at lower WBS levels
Day
Develop Software Tools Training Plan
Day
Review and approve Software Tools Training Plan
Day
Develop EV Concepts Training
Day
Develop Software Tools Training
Day
Write EV Policy Guide
Day
Review and approve EV Policy Guide
Day
Conduct EV Concepts Training for fifty managers
Day
Conduct "practice" customer review
Day
EVMS Review conducted by Customer
Identify and enter into the Project Risk Register worksheet any significant risks to meeting the subproject objective. "Significant risks" are those risks that could be expected to be "approved." Include in the register all risk information by the column headings. For the Risk Rating use the Likelihood times the highest Impact.
Continue the Risk Register form for your answers.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock