Question: You are approximately halfway through a complex construction project and are presenting the data from earned value management analysis of the project to your team.
You are approximately halfway through a complex construction project and are presenting the data from earned value management analysis of the project to your team. You have a BAC of $50,0000, an EV of $2,800,000, an AC of $260,000, and a PV of $250,000. The team members are happy with these figures and want to know the rate at which they have to work to achieve the revised estimate at completion. What is your answer?
A: 1.0 B: 0.92 C: 1.08 D: 0.5
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
