Question: You are currently completing work associated with the process called Validate Scope in the PMBOK Guide. What is this process primarily focused on? A:
You are currently completing work associated with the process called Validate Scope in the PMBOK ® Guide. What is this process primarily focused on?
A: Performing variance analysis on the expected and actual deliverables.
B: Finalizing the project and product scope statement.
C: Formalizing acceptance of the completed project deliverables.
D: Accepting approved change requests and amending the project scope baseline.