Question: You are developing a video game for a client. The cost of the project is 250,000 USD. To date, you have spent 100,000 USD and
You are developing a video game for a client. The cost of the project is 250,000 USD. To date, you have spent 100,000 USD and you have completed the 30% of the project. Upon a review of the project you find that, due to an error, you are over budget and from now onward you can move ahead as planned. What is the EAC of the project?
(a) 425,000 USD
(b) 357,142 USD
(c) 225,000 USD
(d) 275,000 USD Go to the Answer