Question: You are making some changes to the scope and schedule baseline because you have identified a high-impact risk and management does not want to take

You are making some changes to the scope and schedule baseline because you have identified a high-impact risk and management does not want to take a risk. What process is this?

(a) Plan scope management

(b) Plan risk response

(c) Develop schedule

(d) Control scope