Question: You are managing a software development project. The project will involve working with a remote team. One of the requirements is to set up a
You are managing a software development project. The project will involve working with a remote team. One of the requirements is to set up a secure communication link. The lead-time to setup the link is 45 days. Since the initial phase of the project involves requirements gathering, you feel that the link is required only after 3 months and are planning accordingly. You would typically do this planning activity in:
A. The Conduct Procurements process B. The Define Activities process C. The Plan Procurement Management process D. The Control Procurements process