Question: You are managing a software development project. The project will involve working with a remote team. One of the requirements is to set up a
You are managing a software development project. The project will involve working with a remote team. One of the requirements is to set up a secure communication link. The lead time to set up the link is days. Since the initial phase of the project involves requirements gathering, you believe that the link is only required after months and you are planning accordingly. You would typically do this planning activity in:
a
The Control Procurements process
b
The Define Activities process
c
The Plan Procurement Management process
d
The Conduct Procurements process