You are the project manager for a project with a very tight schedule. Because the project is running late, you feel that you do not have time to consider all the possible solutions due to a disagreement between two team members. You quickly decide to side with the team member that has the largest amount of seniority. This is an example of which of the following? ❍ A. Problem solving ❍ B. Compromising ❍ C. Forcing ❍ D. Withdrawal