Question: 2. Nihra is the project manager for a project with a very tight schedule. The project is running late, and Nihra feels that he does
2. Nihra is the project manager for a project with a very tight schedule. The project is running late, and Nihra feels that he does not have time to consider all the possible solutions that two team members are in disagreement over. Nihra quickly decides to go with the team member with the largest amount of seniority. This is an example of which of the following? (1 Point) Problem solving Compromising Forcing Withdrawal Refusing