Question: You are the project manager on a project to develop a new piece of customer management software for an external client. Through your approved change
You are the project manager on a project to develop a new piece of customer management software for an external client. Through your approved change control process you are considering a request to alter the scope of the project. While considering the impact of the request on the project scope, you must also consider the impact on other areas of the project such as quality, schedule, budget, and risk. These other areas that you are considering represent what to the project?
A: Opportunities B: Constraints C: Constrictions D: Risks