Question: You are using parametric estimating techniques to estimate costs for each activity and the total budget in your project. However, a project manager who is
You are using parametric estimating techniques to estimate costs for each activity and the total budget in your project. However, a project manager who is a colleague of you tells you to bump up each estimate by 20% to account for any unknown risks and submit that as a total budget for the customers. What should you do?
A. Do not inflate the estimate B. Inform the customer and then inflate the estimate C. Inflate the estimate first and inform the customer D. Inflate the estimate but do not inform the customer