Question: You are using the one-on-one interview technique to gather high-level risks, assumptions, and constraints in an infrastructure development project to set up a bank. During


You are using the one-on-one interview technique to gather high-level risks, assumptions, and constraints in an infrastructure development project to set up a bank. During the interview process a key stakeholder tells you that the project might end up in failure due to lack of support from the local people. What should you do in this situation?

A. Escalate stakeholder's comments to the sponsor for his advice B. Investigate the reasons behind stakeholder's comments C. Document stakeholder's comments and continue with the project D. Ignore stakeholder's comments and continue with the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!