Question: You are responsible for developing high-level risks, assumptions, and constraints for your project. You meet with experts in your organization and understand various risks in
You are responsible for developing high-level risks, assumptions, and constraints for your project. You meet with experts in your organization and understand various risks in the project. However, you notice a significant risk to the project based on the historical data from a previous project about which nobody is aware of. What should you do to continue the project?
A. Do not document the risk as it is based on past data B. Document but make it a low-level risk C. Document and make it a high-level risk D. Do not document the risk since nobody knows about it