Question: You have been given a big project to complete. This is an important project for your company, therefore management does not want any delay in
You have been given a big project to complete. This is an important project for your company, therefore management does not want any delay in completion. As soon as the project charter is signed, you start identifying and categorizing stakeholders using various data representation tools. Which of the following tools will you not use here?
(a) Brain writing
(b) Stakeholder cube
(c) Direction of influence
(d) Salience model