Question: You have been given a task to estimate a budget for your project. You are using a bottom up cost estimation technique to calculate the

You have been given a task to estimate a budget for your project. You are using a bottom up cost estimation technique to calculate the cost of each activity. Management told you that the management reserve will be 6% of the cost baseline. Which of the following represents the budgeted cost of the project?

(a) Cost Baseline + Management Reserve

(b) Cost Baseline + Contingency Reserve

(c) Contingency Reserve + Management Reserve

(d) None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!