Question: You have been given a task to estimate a budget for your project. You are using a bottom up cost estimation technique to calculate the
You have been given a task to estimate a budget for your project. You are using a bottom up cost estimation technique to calculate the cost of each activity. Management told you that the management reserve will be 6% of the cost baseline. Which of the following represents the budgeted cost of the project?
(a) Cost Baseline + Management Reserve
(b) Cost Baseline + Contingency Reserve
(c) Contingency Reserve + Management Reserve
(d) None of the above