Question: You have completed the work required to develop your cost management plan and are introducing it to your team members so that they are aware
You have completed the work required to develop your cost management plan and are introducing it to your team members so that they are aware of its purpose and limitations. The cost management plan can establish all of the following except?
A: Units of measure B: Level of accuracy C: Activity definition D: Control thresholds