Question: Costs that cannot be directly traced to a specific project and are accumulated and allocated equitably over multiple projects are known as what? A: Indirect

Costs that cannot be directly traced to a specific project and are accumulated and allocated equitably over multiple projects are known as what?

A: Indirect costs B: Direct costs C: Allocatable costs D: Non-projectized costs