Question: You have just started administrating a contract when management decides to terminate the contract. What should you do FIRST? A. Go back to the Plan
You have just started administrating a contract when management decides to terminate the contract. What should you do FIRST? A. Go back to the Plan Procurements process. B. Go back to the Conduct Procurements process. C. Finish the Administer Procurements process. D. Go to the Close Procurements process.