Question: You work for a software development company that has followed the waterfall development model for more than 20 years. Lately, a number of customers have
You work for a software development company that has followed the waterfall development model for more than 20 years. Lately, a number of customers have complained that your company is taking too long to complete its projects. You attended a class on agile development methods and believe that if the company used the agile approach, it could provide products to clients in a shorter time period. However, it would be a major culture change to switch from the waterfall methodology to the agile approach and to train staff members in this new approach. You mentioned this idea to the director of the PMO, and although she liked the idea, she would need approval from the company’s portfolio review board to move forward with it. She suggested that you document this idea in a—
a. Business need
b. Product scope description
c. Project charter
d. Business case
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts