Question: Your organization has received two possible projects. The first project will give you 50,000 USD profit but it is a bit time consuming, and the

Your organization has received two possible projects. The first project will give you 50,000 USD profit but it is a bit time consuming, and the second project will give you 35,000 USD and it will complete earlier than the first project. Therefore, you select the second project. What is the opportunity cost of selecting the second project?

(a) 50,000 USD

(b) 35,000 USD

(c) 85000 USD

(d) 15,000 USD Go to the Answer