Question: Your project is delayed and you have another project to start as soon as possible. You are also having a problem with resource allocating, so
Your project is delayed and you have another project to start as soon as possible. You are also having a problem with resource allocating, so you started reviewing activities to find which activities can be started late and which cannot. On a network diagram, what kind of activities can have the maximum flexibility without causing more delay?
(a) Activities on critical path
(b) Activities with total float
(c) Activities with free float
(d) Hammock activities