Question: Your project is delayed and you have another project to start as soon as possible. You are also having a problem with resource allocating. So
Your project is delayed and you have another project to start as soon as possible. You are also having a problem with resource allocating. So you started reviewing activities to find which activities can be started late and which cannot. On a network diagram, what kind of activities can have the maximum flexibility without causing more delay? a activities on critical path b activities with total float c activities with free float d hammock activities