Question: Your schedule analysis has shown that your project has a high likelihood of experiencing a schedule overrun. You know this because the cumulative EV is
Your schedule analysis has shown that your project has a high likelihood of experiencing a schedule overrun. You know this because the cumulative EV is much: A. Higher than the cumulative AC. B. Higher than the cumulative PV. C. Lower than the cumulative PV. D. Lower than the cumulative CPI.