Question:
Which is the correct formula for computing the overhead rate?
A. Estimated use of the cost driver for production/estimated overhead for the activity
B. Estimated overhead for the product/estimated use of the cost driver for the activity
C. Estimated use of the cost driver for production/estimated overhead for the activity
D. Estimated overhead for the activity/estimated use of the cost driver for the activity