Question: Consider the project described in Problem 3 with the normal and the expedited costs and times given in the following table. Immediate Normal Expedited Normal
Consider the project described in Problem 3 with the normal and the expedited costs and times given in the following table.
Immediate Normal Expedited Normal Expedited Activity Predecessor Time Time Cost Cost A — 3 2 $200 $250 B A 5 3 600 850 C A 1 1 100 100 D B, C 4 2 650 900 E B 3 2 450 500 F E, D 3 2 500 620 G F 2 1 500 600 H E, D 4 2 600 900
a. Consider successive reductions in the project time of one week and find the direct cost of the project after each reduction.
b. Suppose that indirect costs are $150 per week. Find the optimal project completion time and the optimal total project cost.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
