Question: Consider the project described in problem 1 with the normal and the expedited costs and times given in the following table. table [ [

Consider the project described in problem 1 with the normal and the expedited costs and times given in the following table.
\table[[Activity,\table[[Immediate],[Predecessor]],\table[[Normal],[Time]],\table[[Expedited],[Time]],\table[[Normal],[Cost]],\table[[Expedited],[Cost]]],[A,-,3,2,$200,$250],[B,A,5,3,600,850],[C,A,1,1,100,100],[D,B, C,4,2,650,900],[E,B,3,2,450,500],[F,E, D,3,2,500,620],[G,F,2,1,500,600],[H,E, D,4,2,600,900]]
a. Consider successive reductions in the project time of one week and find the direct cost of the project after each reduction.
b. Suppose that indirect costs are $150 per week. Find the optimal project completion time and the optimal total project cost.
 Consider the project described in problem 1 with the normal and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!