Question: Given that a project involves A, B, C, D ... 1; each requiring a completion time, in days, as per the following table. Activities Time
Given that a project involves A, B, C, D ... 1; each requiring a completion time, in days, as per the following table.
Activities Time A 23 B 8 C 20 D 16 E 24 F 18 G 19 H 4 I 10 Given that activity A precedes activities D and E; activities B and D precede aactivity F, activity C precedes activity G; activities B and G precedes activity H, and activities F and G precede activity 1, draw the network and calculate:
(i) Total float
(ii) Free float
(iii) Independent float
(iv) Critical path
(v) Project completion time