Question: In single machine scheduling problem with single processor, will be constant. (a) Mean flow time (b) Mean tardiness (c) Makespan (d) None of the above.

In single machine scheduling problem with single processor, will be constant.

(a) Mean flow time

(b) Mean tardiness

(c) Makespan

(d) None of the above.