Question: You are a project manager for a project developing a new software application. You have just learned that one of your programmers is adding several

You are a project manager for a project developing a new software application. You have just learned that one of your programmers is adding several new features to one of the deliverables. What is the best action to take?

A. Make any needed adjustments to the schedule and cost baseline and tell the programmer that any future changes must be approved by you.

B. Request that the programmer remove the coding for the new features because they are outside the boundaries of the original scope statement.

C. Contact the appropriate functional manager and request a replacement for this programmer.

D. Determine the source of the request for the new features and put this change through the change control process to determine the impact of the changes and obtain formal approval to change the scope.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Framework Questions!