Question: You have recommended using an agile methodology for a project the organization is ready to move to the Executing phase. This is a large, complex
You have recommended using an agile methodology for a project the organization is ready to move to the Executing phase. This is a large, complex project and will require more than one agile team.
You decide to use a methodology whereby each agile team will consist of three to nine members, they will all work on the same project but will have their own backlog to work from, and you will hold a daily standup with all the teams whereby one representative from each team will join the collective standup meeting. What methodology is this describing?
A. DA B. PRINCE2 C. Scrum of Scrums D. SAFe
Step by Step Solution
There are 3 Steps involved in it