Question: Your vendor is contesting a recent change request. They believe they implemented the change as requested; the project team believes the change is not functioning

Your vendor is contesting a recent change request. They believe they implemented the change as requested; the project team believes the change is not functioning as required. Which of the following documents, monitors, and manages these types of contested changes?

A. Contested change control B. Contract change control system C. Claims administration D. Compensation administration