Question: 13.44 A software coding project was scheduled to be finished today, after 12 weeks of work. You receive an updated EVM report on the progress
13.44 A software coding project was scheduled to be finished today, after 12 weeks of work. You receive an updated EVM report on the progress of the coding suggesting that it has a schedule performance index (SPI) value of .75.
Based on this information, when do you expect the coding to be finished?