Question:
A software coding project was scheduled to be finished today, after 12 weeks of work. You receive an updated EVM report on the progress of the coding suggesting that it has a schedule performance index (SPI) value of .75.
Based on this information, when do you expect the coding to be finished?
a. One week early
b. In one more week
c. In two more weeks
d. In four more weeks