Question: A project network has five pathsP1, P2, P3, P4 and P5. The total activity duration computed along each of these paths are22, 31, 20, 30
A project network has five paths—P1, P2, P3, P4 and P5. The total activity duration computed along each of these paths are—22, 31, 20, 30 and 19 days, respectively. What is the minimum duration for project completion?