Question: The mean time for project completion using PERT method of time estimation is 25 weeks with a standard deviation of 3 weeks. What is the

The mean time for project completion using PERT method of time estimation is 25 weeks with a standard deviation of 3 weeks. What is the duration beyond which the project completion is not likely to extend?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock