Question: Cost estimating should occur: a. Before the work breakdown structure is created and before the budget is developed b. Before the work breakdown structure is

Cost estimating should occur:

a. Before the work breakdown structure is created and before the budget is developed

b. Before the work breakdown structure is created and after the budget is developed

c. After the work breakdown structure is created and before the budget is developed

d. After the work breakdown structure is developed and after the budget is developed

Step by Step Solution

3.41 Rating (145 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

cThe project cost estimates ... View full answer