If BAC = $12,000 and CPI = 0.8, what is the variance at completion? A. $2000 B.
Question:
If BAC = $12,000 and CPI = 0.8, what is the variance at completion?
A. –$2000
B. +$2000
C. –$3000
D. +$3000
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management A Systems Approach To Planning Scheduling And Controlling
ISBN: 9781119805373
13th Edition
Authors: Harold Kerzner