If BAC for a work package is $10,000 and BCWP = $4,000, then the work package is:
Question:
If BAC for a work package is $10,000 and BCWP = $4,000, then the work package is:
A. 40 percent complete
B. 80 percent complete
C. 100 percent complete
D. 120 percent complete