If BAC = $12,000 and CPI = 1.2, then the variance at completion is: A. $2,000 B.
Question:
If BAC = $12,000 and CPI = 1.2, then the variance at completion is:
A. –$2,000
B. +2,000
C. –$3,000
D. +$3000
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 60% (5 reviews)
Answered By
Kainat Shabbir
i am an experienced qualified expert with a long record of success helping clients overcome specific difficulties in information technology, business and arts greatly increasing their confidence in these topics. i am providing professional services in following concerns research papers, term papers, dissertation writing, book reports, biography writing, proofreading, editing, article critique, book review, coursework, c++, java, bootstarp, database.
5.00+
184+ Reviews
255+ Question Solved
Related Book For
Project Management A Systems Approach To Planning Scheduling And Controlling
ISBN: 9781119165354
12th Edition
Authors: Harold Kerzner
Question Posted:
Students also viewed these Business questions
-
If BAC = $12,000 and CPI = 0.8, then the variance at completion is: A. $3,000 B. +$2,000 C. $3,000 D. $3,000
-
You and your spouse have purchased a foreclosure you hope to flip for a profit. The two bathrooms had been recently remodeled by the previous owners. The three bedrooms need only cosmetic work -...
-
The data identified below was listed in a projects latest status report: BCWS = $36,000 BCWP = $30,000 ACWP = $33,000 BAC = $120,000 Original length of the project 10 months Using these data,...
-
It is stated in Section 40.3 that a finite potential well always has at least one bound level, no matter how shallow the well. Does this mean that as U 0 0, E 1 0? Does this violate the Heisenberg...
-
Numerous IT projects are staffed with virtual teams. How do these virtual teams differ from traditional teams?
-
Futura Company purchases the 40,000 starters that it installs in its standard line of farm tractors from a supplier for the price of $8.40 per unit. Due to a reduction in output, the company now has...
-
Differentiate between a fast and loose pulley.
-
4. (Chapter 3) Skycell, a major European cell phone manufacturer, is making production plans for the coming year. Skycell has worked with its customers (the service providers) to come up with...
-
Suppose a Summons and Complaint were filed on February 16, 2021 and personally served on the defendant on March 1, 2021, please calendar the following dates: a the day Proof of Service of Summons and...
-
Your manufacturing team informs you that they have found a way to increase the size of the manufacturing run from 10,000 to 18,000 units in increments of 2000 units. However, the setup cost will be...
-
Barbara just received the good news: She was assigned as the project manager for a project that her company won as part of competitive bidding. Whenever a request for proposal (RFP) comes into...
-
Some cruise ship passengers are given magnetic bracelets, which they agree to wear in an attempt to eliminate or diminish the effects of motion sickness. Others are given similar bracelets that have...
-
An infant's toy has a 1 2 0 gwooden animal hanging from a spring. If pulled down gently, the animal oscillates up and down with a period of 0 . 5 6 s . His older sister pulls the spring a bit more...
-
You have just been hired as a new management accountant by UMW Holdings Berhad. In the past, the company has done very little in the way of budgeting and at certain times of the year has experienced...
-
Sri Lanka debt crisis was due to the economic mismanagement. Sri Lanka's current debt to GDP had skyrocketed from 42% in 2019 to 104% in 2021.According to Bloomberg, Sri Lanka has about $8.6 billion...
-
Apply Rostow's Linear Growth Theory to economic growth in your country. According to this theory, at what stage of growth in South Africa? Substantiate the answer. Apply each growth stage to South...
-
Discuss the primary reasons for accidents in the laboratory and practices used to reduce the risk of accident occurrences. Differentiate the responsibilities of the employee and employer in a...
-
Bar Corporation has been looking to expand its operations and has decided to acquire the assets of Vicker Company and Kendal Company. Bar will issue 30,000 shares of its $10 par common stock to...
-
An auto-parts manufacturer is considering establishing an engineering computing center. This center will be equipped with three engineering workstations each of which would cost $25,000 and have a...
-
Jones Construction Company has recently won a $120 million effort for a local company. The effort includes three separate construction projects, each one beginning at the same time. Two of the...
-
Several years ago, Minnesota Power and Light established priorities as follows: Level 0: no priority Level 1: to be completed on or before a specific date Level 2: to be completed in or before a...
-
Richard is a department manager who must supply resources to four different projects. Although each project has an established priority, the project managers continually argue that departmental...
-
Delaware Medical Center operates a general hospital. The medical center also rents space and beds to separately owned entities rendering specialized services, such as Pediatrics and Psychiatric Care....
-
Prepare entries to record the following non - strategic investment transactions of Arrowhead Investment Corporation. ( If no entry is required for a transaction / event , select " No journal entry...
-
The following income statement and balance sheet information is available for the operating segments of Bogart, Inc. Operating Segments ( In millions of dollars ) Grant Stewart Kelly Flynn Cagney...
Study smarter with the SolutionInn App