Question: The data identified below was listed in a projects latest status report: BCWS = $36,000 BCWP = $30,000 ACWP = $33,000
● BCWS = $36,000
● BCWP = $30,000
● ACWP = $33,000
● BAC = $120,000
● Original length of the project 10 months
Using these data, calculate the following:
a. What are the values for CPI and SPI?
b. What is the expected cost at completion (EAC)?
c. How much money will be needed from the time of the report to complete the project?
d. What is the cost variance at completion (VAC)?
e. Using SPI, what is the new expected length of the project?
Step by Step Solution
3.27 Rating (168 Votes )
There are 3 Steps involved in it
SPI 0833 and CPI 090909 ... View full answer