Question: The data identified below was listed in a projects latest status report: BCWS = $36,000 BCWP = $30,000 ACWP = $33,000

The data identified below was listed in a project’s latest status report:
● BCWS = $36,000
● BCWP = $30,000
● ACWP = $33,000
● BAC = $120,000
● Original length of the project 10 months
Using these data, calculate the following:
a. What are the values for CPI and SPI?
b. What is the expected cost at completion (EAC)?
c. How much money will be needed from the time of the report to complete the project?
d. What is the cost variance at completion (VAC)?
e. Using SPI, what is the new expected length of the project?

Step by Step Solution

3.27 Rating (168 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

SPI 0833 and CPI 090909 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

93-B-M-L-P-M (894).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!