Question: In the original network diagram question, if Activity D increases from four to five days, what is the critical path, and what is the length?

In the original network diagram question, if Activity D increases from four to five days, what is the critical path, and what is the length?

a. BDE, 33 days

b. ACE, 15 days

c. BFG, 21 days

d. BDG, 23 days