Question: Microsoft Project Presentation Microsoft Project is a popular project planning utility. The table below shows a sample output from that utility. Use the data shown
Microsoft Project Presentation Microsoft Project is a popular project planning utility. The table below shows a sample output from that utility.

Use the data shown in the MS Project output to answer the following questions:
a. What is the current cost status?
b. What is the current schedule status?
c. Why is EV value zero?
d. Given these parameters, how much overrun would you expect for cost and schedule?
Baseline Actual Duration 1 Task Name EV Proj 25 days $5,000 $4,000 Cost % Cost Complete CPI Cost 45% 0.67 $2,250 $1,500 $3,000 0.5 $6,000 20, 08 EV/BCWF PV/BCWS SPI EAC Jun 1, '08 May 4, '08 May 18, 08 TMFTS WSTMFT 2 A 15 days $3,000 $2,000 75% 0.67 $2,250 $1,500 $2,000 0.75 $3,000 $3,000 $2,000 3 B 10 days $2,000 $2,000 0% 0 $0 $0 $1,000 0 $2,000 $2,000 $2,000
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
