Reducing the peaks and valleys in manpower assignments in order to obtain a relatively smooth manpower curve
Question:
Reducing the peaks and valleys in manpower assignments in order to obtain a relatively smooth manpower curve is called:
A. Manpower allocation
B. Manpower leveling
C. Resource allocation
D. Resource commitment planning